Site Clearing Project

Client: Transportation Corporation

Location: Bronx, New York

Project Description: K3 Complete performed site clearing activities related to an approximate one mile strip of land approximately 80’ wide along a major highway.  This end use of this project was a proposed “rails to trails” property.  The site clearing activities included clearing & grubbing all underbrush and ground vegetation; the collection and removal of all trash and debris from the entire site and off-site disposal; the installation of imported approximately 3,000 CY of mulch to cover the entire site.

Project Duration: The project started in July, 2017 through November, 2017

Project Cost: The total project construction cost was approximately $650,000.